Organization Change

скачати

Organization Change Essay, Research Paper

It is intended that this organizational review, will provide the Districts with a better understanding of the changing process computer hardware and software support needs. Also to review the department location for the Plant Automation Group (Group), and develop recommendations on the proposed reporting relationships.

? Review the background information.

? Identify the primary and secondary functions of the Plant Automation Group

? Review possible location of the Plant Automation Group.

? Identify and review reporting relationships options

DEFINITIONS

Definitions used within this organizational review.

SCADASupervisory and Data Acquisition System

PLCProgrammable Logic Controller

HMIHuman Machine Interface

ITDInformation Technology Department

PAGPlant Automation Group

GMGeneral Manager

BACKGROUND

When the Districts first began consideration to form a focal group with responsibility for Plant Automation, a task force was formed to make recommendations. The one recommendation this task was unable to come to agreement on was the location of this new Plant Automation Group (PAG). An executive decision was made by the General Manager to center the PAG in the Information Technology Department (ITD).

In September 1994, the Joint Board contracted with Ernst & Young to produce a “Management Review of the Proposed Plant Automation Group for the Sanitation Districts of Orange County”. Their report recommended the location be with ITD but noted that for the duration of the J-31 project, some engineering-related activities would be involved and require close coordination with the Engineering Department. As late as July 1995 when Ernst & Young performed the Finance Function Review (which included the Information Services Division), they echoed their previous recommendation but provided a timeline of approximately two years to revisit the issue of PAG’s location. However, this was not a firm recommendation.

Over the past several months, a number of problems have made it clear that the two year time frame identified in the Ernst & Young report may have been optimistic. The problems of budget management, close coordination and communication have placed a strain on the existing management of the ITD, creating frustration and numerous problems throughout many parts of the organization.

Primary Functions

The charter of the Plant Automation focuses on:

? Support of the Operations Division

? Providing engineering integration assistance through software and hardware analysis and the setting of standards

? Support of the Maintenance Division regarding system and software modifications and changes

? Assisting in the roll-out of the J-31 contract so that a transfer of knowledge between CH2M Hill and the Districts occurs

? Analyzing and the recommendation of system and network architecture, system design, and integration proposals.

The Plant Automation Group is made up of a number of disciplines. Process control programming is very different from the type of programming which Information Technology has been doing and requires different education, skills, and experience. These skill sets all need to be integrated and unified for the purposes of process control. Skills required include the administration of VAX computer environments, configuration, computer operations, data communications for Ethernet and report generation.

The Plant Automation Group also covers PLC development and programming, HMI development, and data communications required for PLCs. It is also necessary to perform software development for process control systems, either personally or by assuming oversight responsibility for contractual development. Once a system is in place, this is a task which cannot be contracted out due to the highly customized nature of the process control software (Square D, CRISP SCADA) design.

The Plant Automation Group is also required to be on-call 24 hours a day in support of the Operations and Maintenance Departments; and is a resource to all other departments, providing technical support which primarily focuses on control system and data integration.

Secondary Functions

The Plant Automation Group was chartered with an additional task, outside of their normal work responsibilities, the design of the J-31 Projects. These projects were expanded to include the development of a set of working software programming standards including CRISP, Human Machine Interfaces, Programmable Logic Controller Ladder Logic, and documentation at the conclusion of this project.

Location of The Plant Automation Group

Considerable debate has surrounded the location of the Plant Automation Group and the J-31 Project. Each of the four departments has a vested interest in this function:

A. Operation?s interest is as a natural outgrowth of being the primary recipient of our group?s effort, and the department most concerned with its success.

B. Maintenance?s interest is due to its existing responsibilities in PLC maintenance through its Instrumentation Maintenance Division.

C. The Engineering Department?s interest is due to their staff?s concern in the proper design of treatment processes, and facilities to optimize the treatment of wastewater by the Districts.

D. Information Technology is concerned with the management of the Districts? computing and communication resources for the benefit of all of these departments.

Reporting Relationship

There are three basic options, at this point in time:

1. The first option is to maintain the Plant Automation Group, as presently defined, but change its organizational structure. At the present time it is organized as a separate group within Division 2430, the Software Support and Plant Automation Division. This has not worked well at all as the activities are too varied to be able to manage adequately. If no other change is forthcoming, it should be proposed that the Plant Automation Group be split so that the Software Support Division and the Plant Automation Division be two separate divisions. The new Plant Automation Division would be staffed with a Division Manager whose role would be to provide the appropriate direction, coordination, administration, and budgetary oversight to this important role. The advantage of this approach is that, given the right manager, many of the problems which have been experienced to date should be alleviated. The disadvantage is that it may only bury the problems in another layer of bureaucracy — much will hinge on the management abilities of the new Division Manager.

2. The second option is to transfer the Plant Automation Group, in its entirety, to the Engineering Department. Within Engineering, it should enable the proper coordination and communication to occur for the elements of the PAG’s activities that involve design. The disadvantage of this approach is that the only design element of PAG left is the remaining portion of J-31. When this project is completed, no further engineering-related activities will remain. At the present time, PAG is beginning to assume a 24-hour, on-going support function which is not consistent with the Engineering Department’s normal activities. The most important role that the Plant Automation Group fulfills is that of System Integration for Plant Automation. This activity is intimately attuned to the activities of the Information Technology Department, although for a uniquely different application than what the rest of the ITD is involved with.

3. The third option is to immediately transfer what small portion remains of the J-31project to the Engineering Department for the duration of the project. The PAG will then continue in ITD and become a separate Division, as outlined in Option 1 above. The new Plant Automation Division would immediately assume the sole function of supporting plant automation and make recommendations to Engineering regarding future construction projects, in the same way that Operations and Maintenance have always done. The advantage of this approach is to allow Engineering to manage this project and get the Plant Automation Group out of the business of Engineering. The only disadvantages are that a change in project management mid-stream might result in some loss of momentum and coordination difficulties. The other possible disadvantage may be a lack of staffing in Engineering. Naturally, some support staff should be loaned to Engineering from the Plant Automation Group to enable this transition to succeed.

RECOMMENDATION

The Plant Automation Group will only succeed through the combined effort of all the departments. It must be allowed to focus on selected critical objectives. Initially, it must focus on:

? Making Operations its primary customer

? Learning and analyzing new system architectures, hardware, and software

? Understanding and learning how to support and maintain the new systems arising from the J-31 contracts

? Reviewing and participating on proposed projects, writing and testing software standards for the entire organization to use.

The location of the Plant Automation Group should be based on its primary work function, which is mainly computer software and hardware support.

The J-31 Projects have two very distinct parts – Traditional Design and Software Integration. For the J-31 projects to be successful, cooperation and assistance must be fostered between the departments. A team-like approach to problem resolution is fundamental to building a responsive organization. The Districts should employ the concept of “Concurrent Engineering,” which solicits the input and commitment of all relevant departments in the conception and design stages. Concurrent Engineering allows for all parts of an organization to be included in the initial phases of a project, in order to identify and address problems early before change involves a great expense. Involving participants together enriches the final product.

The best solution will center the traditional design portion of J-31 in the Planning and Design Group of the Engineering Department, and Software Integration within the Plant Automation Group. This same approach should be used for any future follow-on projects involving automation for Plant Operations. This dual responsibility will reduce each department’s exposure and vulnerability in dealing with skill sets outside of their normal working environment.

Option 3 should be adopted as being the best solution to the problems identified and I would recommend implementation of this option.

REFERENCES

Banner, D. K., Gagn?, E. T. (1996). Designing Effective Organizations. Thousand Oaks, CA: Sage Publications.

Robbins, S. (1996). Organizational Behavior: Concepts, Controversies, Applications. Englewood Cliffs, NJ: Prentice-Hall Inc.

Fisher, D. (1993). Communication in Organization. St. Paul, MN: West Publishing Co. Purchased:

Hersey, P. (1996). Management of Organizational Behavior. Englewood Cliffs, NJ: Prentice-Hall Inc.

Steers, R. (1993). Organizational Behavior. Glenveiw, IL: Scott, Foresman and Company.

Timm, P. (1992). Supervision. St. Paul, MN: West Publishing Co.

Smeltzer, L., Leonard, D. (1994). Managerial Communication: Strategies and Applications

Додати в блог або на сайт

Цей текст може містити помилки.

A Free essays | Essay
16.8кб. | download | скачати


Related works:
Social organization
Coping With Stress In An Organization
Palestinian Liberation Organization
Palestinian liberation organization
Organization structure of Visa
Individual Organization Behavior
The Organization Of African Unity
Forms Of Organization In Business
The Daewoo Group Organization
© Усі права захищені
написати до нас